Close Menu
Metals Weekly
    TRENDING -
    • Impact of deep-sea mining on seafloor ecosystem still evident 44 years later
    • Congo opens mining fraud inquiry after copper and cobalt seizures, statement shows
    • Latin American Countries Take Mining Pollution Claims To Human Rights Court
    • Critical minerals are more than mining
    • US strategy links Myanmar peace talks to rare-earth access
    • Can a new design save one of Minnesota’s most controversial mining projects?
    • Carbon footprint of metal production could be more than 10 times higher than estimated
    • Metals and mining outlook 2026: half-time report
    Metals Weekly
    • Home
    • Critical Materials
    • Environment
    • Global Policy
    • Mining
    Metals Weekly
    Home»Mining»Generation Mining nears $1B copper project funding

    Generation Mining nears $1B copper project funding

    Mining 5 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
    Share
    Facebook Twitter LinkedIn Pinterest Email

    Generation Mining (TSX: GENM; US-OTC: GENMF) has assembled almost all its financing for the $1-billion capex Marathon copper-palladium project in northern Ontario.

    The $969 million total includes $200 million this week from the Canadian Infrastructure Bank (CIB), $424 million in senior debt from several lenders and a $240-million streaming deal with Wheaton Precious Metals (NYSE, TSX, LSE: WPM). That leaves about $150 million to be potentially raised through equity this fall, according to Haywood Securities mining analyst Pierre Vaillancourt. Construction would start in next year’s first half.

    “With permitting and most of the financing complete, Generation is in good position to move the project forward,” Vaillancourt said in a note on Tuesday. “With copper at about $6.30 per lb. and palladium at $1,250 an oz., economics for Marathon are compelling, supported by strong copper revenues.”

    Marathon, located on the north shore of Lake Superior, would be one of Ontario’s first critical minerals projects to enter production in years with its planned 2028 start. It would be one of North America’s few sources of palladium for hybrid and electric vehicles, and a top-five copper producer in the province. Generation has locked in offtake agreements for half of its 42-million-lb.-a-year copper output to Glencore (LSE:GLEN) to and the rest to an undisclosed European integrated group.

    Federal funds

    “It’s really, really rare that a company with a $200-million market cap is attempting to build an almost $1-billion capex mine,” Generation Chairman Kerry Knoll told The Northern Miner in a video call Tuesday. “Fortunately, the federal government, which wasn’t really there historically to help the mining industry, has stepped up in a big way.”

    The Generation deal with CIB follows the fund’s $55-million bridge loan for Torngat Metals’ Strange Lake rare earths project and Nouveau Monde Graphite’s (NYSE: NMG, TSX: NOU) $459-million debt financing earlier this year. The CIB, a government lender with $18 billion supporting development across Canada, has a renewed focus on junior miners and has pivoted this year from base metals and gold to critical minerals.

    The CIB is providing $110 million in subordinated construction debt and a $90-million standby facility to cover overruns at Marathon. That was just days after Generation obtained the senior debt from Export Development Canada, ING Capital and Société Générale. The junior had previously secured $145 million in equipment leasing facilities.

    “It’s definitely very helpful to have the subordinated debt from a Crown Corporation to validate the worthiness of this project,” President and CEO Jamie Levy said in the same video call. “The subordinated debt was necessary for this project to happen.”

    28% IRR

    Located near the namesake town, Marathon is about 300 km east of Thunder Bay. In addition to the copper, it would annually produce 168,000 oz. of palladium, 38,000 oz. of platinum, 12,000 oz. of gold and 240,000 oz. of silver, over its 13-year life, according to an updated 2025 feasibility study. The study showed an after-tax net present value of $1.07 billion and an internal rate of return of 28%, with estimated construction costs of $992 million.

    Under the 2021 streaming deal, Wheaton will get the first 150,000 oz. of payable gold and 67% of yellow metal production over the remaining life of the mine. It will also receive 22% of payable platinum up to 120,000 oz. and 15% for the remaining life. Wheaton has provided Generation the first $40 million with the rest available during construction.

    Glencore could process the concentrate at its Horne smelter in western Quebec and Canadian Copper Refinery outside Montreal – together Canada’s only complete copper-smelter and refinery chain.

    Generation closed a $34.5-million bought deal in January and has $40 million in cash, according to its March earnings statement. Host community Biigtigong Nishnaabeg First Nation has also injected $750,000 under a February private placement. Generation’s executives are confident in the company’s ability to attract the needed investment based on due diligence undertaken by its institutional lenders since Marathon received its final construction permit in May 2025.

    Shares in Generation Mining have gained 8.3% over the past month to 65¢ apiece on Thursday, valuing the company at $210 million. The stock has traded in a 52-week range of 28¢ to 92¢.

    Ready to go

    In anticipation of completed financing, Knoll said the company’s detailed engineering work started in January for a September preconstruction start. Generation and its construction contractor Ausenco Engineering Canada have been negotiating final pricing and making downpayments on certain long-lead items.

    “We’re about one third of the way through the spend, in terms of negotiating a final price on things, for example, the heavy equipment, the transformers,” said Knoll. “The good news is that we’re a little bit under the feasibility estimates at this point. Of course, there is still more to go and there will be some negative surprises, there always are, but we’re getting some positive surprises, which is fantastic.”

    Knoll said Generation has soil sampling, prospecting and mapping work planned this summer. The trend is 30 km long with mineralization spots along the way, including the Geordie and Sally deposits. He said it could hold potential for underground mining, as opposed to the outcrops discovered to date.

    “Down the road, we would love to expand this mine so it could last for numerous generations but that’s a long way away from getting into production and is not permitted,” Levy said regarding potential on the company’s 364-sq.-km land package. “Our focus now is getting this project built from what is permitted in our environmental assessment.”

    By – https://www.northernminer.com/news/generation-mining-nears-1b-copper-project-funding/1003892484/

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

    Related Posts

    Congo opens mining fraud inquiry after copper and cobalt seizures, statement shows

    US strategy links Myanmar peace talks to rare-earth access

    $1M from DOE goes toward attracting mining talent

    Don't Miss

    Diesel Price Volatility Squeezes Mining Margins in Mexico

    Global Policy 5 Mins Read

    Global diesel price volatility and refining bottlenecks are increasing production costs across mining operations in…

    Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’

    Ghana bill would give state special share rights in mining firms, draft shows

    Nigeria mining crackdown under fire after 37 die

    Top Stories

    Metals and mining outlook 2026: half-time report

    You’ve got ore: Alaska’s tungsten history

    European Commission picks 46 new strategic critical mineral projects

    Critical Minerals Refining Gap to Test Deep-Sea Mining Ambitions

    Our Picks

    Zambians pay price amid Copperbelt mining boom

    Zambia says privacy, minerals concerns stall US health aid deal

    Zambia says it is negotiating US minerals deal after ‘decoupling’ from health pact

    Don't Miss

    An Indestructible New Alloy Is Defying the Limits of Metal

    The upward trend in smelting acid prices has persisted for over half a year, with further room for growth

    Zambia says privacy, minerals concerns stall US health aid deal

    Weekly Newsletter

    Subscribe to our weekly Newsletter to keep up to date on the latest news in the metals, minerals and mining industry

    Copyright © 2025 - Metals Weekly. All Rights Reserved.

    Type above and press Enter to search. Press Esc to cancel.