Close Menu
Metals Weekly
    TRENDING -
    • Impact of deep-sea mining on seafloor ecosystem still evident 44 years later
    • Congo opens mining fraud inquiry after copper and cobalt seizures, statement shows
    • Latin American Countries Take Mining Pollution Claims To Human Rights Court
    • Critical minerals are more than mining
    • US strategy links Myanmar peace talks to rare-earth access
    • Can a new design save one of Minnesota’s most controversial mining projects?
    • Carbon footprint of metal production could be more than 10 times higher than estimated
    • Metals and mining outlook 2026: half-time report
    Metals Weekly
    • Home
    • Critical Materials
    • Environment
    • Global Policy
    • Mining
    Metals Weekly
    Home»Environment»Environmentalists Sue Federal Agencies Over Nation’s First Fast-Tracked Critical Minerals Mine

    Environmentalists Sue Federal Agencies Over Nation’s First Fast-Tracked Critical Minerals Mine

    Environment 5 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
    Share
    Facebook Twitter LinkedIn Pinterest Email

    In the foothills of southern Arizona’s Patagonia Mountains, atop so-called critical minerals such as zinc, is South32’s Hermosa project. The first mine added to a federal program designed to speed up permitting, it “set the standard for what the modern federal permitting process should look like” with “clear timelines, real transparency, and comprehensive interagency coordination,” federal officials said after approving it this summer.

    Environmental groups called it an illegal rush job that will harm vulnerable species. Now, two are suing the U.S. Forest Service and U.S. Fish and Wildlife Service over the approval.

    The federal government’s haste to finish environmental review for the mine via a program known as FAST-41, the lawsuit claims, led to permitting “riddled with inconsistencies, ambiguities, and legal violations” under the Endangered Species Act and another landmark law, the National Environmental Policy Act.

    The agencies’ review found the mine would likely adversely affect 10 endangered or threatened species, such as the jaguar and Mexican spotted owl, through impacts to the species or their critical habitat in the project area. The federal government cited yet-to-be-developed mitigation measures when it approved the mine anyway, a violation of the law for nine of those 10 affected species, the lawsuit claims. The plaintiffs also allege the agencies failed to analyze impacts to the local community, such as the mine’s effects on groundwater supplies.

    “Federal agencies that are supposed to protect public lands and endangered animals are planning to sacrifice one of the most important wildlife corridors in the Southwest,” said Russ McSpadden, Southwest conservation advocate at the Center for Biological Diversity, in a statement. The group sued along with the Patagonia Area Resource Alliance.

    “Once these mountains are carved up and their aquifers depleted, there’s no putting them back together,” McSpadden added. “The Patagonia Mountains are worth far more as a thriving ecosystem than they’ll ever be worth to a giant mining company.”

    The U.S. Department of Justice, which represents federal agencies in lawsuits, did not respond to a request for comment. Pat Risner, president of South32 Hermosa, said in a statement that the federal environmental review “incorporated extensive public input and resulted in meaningful project refinements, additional environmental protections, and a stronger project.”

    “We remain confident in the rigor and thoroughness of both the U.S. Forest Service and Fish and Wildlife Service’s review and administrative record and the integrity of the federal review process,” Risner added.

    The Patagonia Mountains are part of a series of ranges known as Arizona’s Sky Islands. They serve as a wildlife corridor from the Rocky Mountains to the Sierra Madre range in Mexico, and represent some of the United States’ most biodiverse hotspots. The area is the only migration corridor in 120 miles for endangered jaguars and ocelots crossing the U.S.-Mexico border.

    South32’s Hermosa mine was approved by the Forest Service in July. The underground mine will extract zinc, lead and silver, with the potential for manganese and copper. Most of the project is on private land and construction is more than halfway complete. The project site contains one of the world’s largest undeveloped zinc resources and enough battery-grade manganese to meet all current domestic demand, according to the company.

    The federal approval lets the company build a primary access road across Coronado National Forest to avoid sending traffic through the town of Patagonia. The government also permitted a 138-kilovolt transmission line to power the mine and a 225-acre tailings facility where mine waste will be stored.

    However, the project has encountered major hurdles this year, with capital costs increasing by 50 percent, from $2.2 billion to $3.3 billion. The company pushed production back a year, to 2028.

    South32 has also seen pushback from the local community. The town of Patagonia, city of Nogales and Santa Cruz County are in active talks to form a community benefits agreement with the mine. Patagonia has positioned itself as a destination for birders and hikers, and residents worry the mine will reduce tourism. And there are major concerns over the mine’s water use.

    Over the mine’s projected 70-year life, an estimated 195,000 acre-feet of water would be removed from the aquifer. One acre-foot is 325,851 gallons, enough water for two to three households a year. That use will draw down the local water table by 250 feet, stretching across nearly 50 square miles and affecting wells within a three-mile radius of the mine, according to the federal environmental impact statement.

    Arizona found the company exceeded permitted antimony levels after it dumped treated groundwater from mine construction into a creek. Those levels have declined since South32 made additional investments in its wastewater treatment plant, but that hasn’t resolved local concerns.

    “Communities across the country should understand: this is just the beginning,” Anna Darian, executive director of Patagonia Area Resource Alliance, said in a statement. “Hermosa may be the first hardrock mining project approved under FAST-41, but it is being held up as a model for what comes next. The long-term effects of weakening or waiving environmental protections could have irreversible consequences for frontline communities like ours.”

    By – https://insideclimatenews.org/news/29092026/federal-fast-tracked-south32-mine-lawsuit/

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

    Related Posts

    Impact of deep-sea mining on seafloor ecosystem still evident 44 years later

    Latin American Countries Take Mining Pollution Claims To Human Rights Court

    Carbon footprint of metal production could be more than 10 times higher than estimated

    Don't Miss

    Diesel Price Volatility Squeezes Mining Margins in Mexico

    Global Policy 5 Mins Read

    Global diesel price volatility and refining bottlenecks are increasing production costs across mining operations in…

    Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’

    Ghana bill would give state special share rights in mining firms, draft shows

    Nigeria mining crackdown under fire after 37 die

    Top Stories

    Metals and mining outlook 2026: half-time report

    You’ve got ore: Alaska’s tungsten history

    European Commission picks 46 new strategic critical mineral projects

    Critical Minerals Refining Gap to Test Deep-Sea Mining Ambitions

    Our Picks

    Zambians pay price amid Copperbelt mining boom

    Zambia says privacy, minerals concerns stall US health aid deal

    Zambia says it is negotiating US minerals deal after ‘decoupling’ from health pact

    Don't Miss

    Hidden deep-sea mining exploration brought to new light

    Scientists Discover a New Way To Control Metals at the Atomic Scale

    Arctic Mine gains FAST-41 permitting status

    Weekly Newsletter

    Subscribe to our weekly Newsletter to keep up to date on the latest news in the metals, minerals and mining industry

    Copyright © 2025 - Metals Weekly. All Rights Reserved.

    Type above and press Enter to search. Press Esc to cancel.