Close Menu
Metals Weekly
    TRENDING -
    • A red flower found nowhere else loses ground as mining expands in Brazil’s Amazon
    • New Venezuelan Mining Law Obscures Old Corruption Problems
    • Rethinking Environmental Clearance for Critical Mineral Mining
    • Malawi government suspends coal miner’s license over river pollution
    • Environmental group sues US Interior for approving rare earth mining in Mojave Desert
    • US companies eye Congo mining assets, including Rubaya, State Dept official says
    • Seabed mining talks show key issues remain unresolved
    • Vancouver-based mining company confirms the deaths of 9 of 10 workers kidnapped in Mexico
    Metals Weekly
    • Home
    • Critical Materials
    • Environment
    • Global Policy
    • Mining
    Metals Weekly
    Home»Environment»Forest Service releases Final Environmental Impact Statement for Hermosa Mine Project near Patagonia

    Forest Service releases Final Environmental Impact Statement for Hermosa Mine Project near Patagonia

    Environment 3 Mins Read
    Facebook Twitter Pinterest LinkedIn Tumblr Reddit Telegram Email
    Share
    Facebook Twitter LinkedIn Pinterest Email

    The federal report details environmental impacts and opens a 45-day objection window before a final decision is expected in July.

    The Final Environmental Impact Statement for the Hermosa Critical Minerals Project – a mine that’s located outside of the town of Patagonia – is now available to the public.

    The 759-page document evaluates environmental impacts from mining activities on federal lands. It also responds to community input that was obtained when the draft impact statement was published.

    Hermosa Project President Pat Risner says that South32 – the Australian mining and metals company in charge of Hermosa – has committed to almost 140 additional conservation, mitigation and monitoring measures that were not in the initial draft document.

    “Working in collaboration with the agencies, tribes and what we’ve heard from community stakeholders to address impacts,” he said.

    Some of these newly proposed actions include an alternate power source via transmission line on Coronado National Forest land, instead of onsite generators as a way to reduce emissions.

    Additional proposed actions also include an alternative tailings storage facility location to avoid impacts on sensitive species, as well as alternative water discharge points.

    “A significant community input we had early on was the discharge from the water treatment plant; they wanted [it] distributed more broadly in the Patagonia mountains, rather than putting it all into Harshaw Creek,” Risner said.

    A 45-day objection period has opened, which means those who commented on the draft statement are able to comment again, before the Forest Service issues a final Record of Decision on the project which is expected in July.

    The Forest Service also published its Draft Record of Decision concurrently with the Final EIS.

    Environmental advocacy groups remain skeptical about the project.

    Russ McSpadden, Southwest conservation advocate with the Center for Biological Diversity called the project a nightmare for the Patagonia Mountains, a known biodiversity hotspot that includes designated critical habitat for jaguars and other endangered species.

    “This company has a permit to drain 4,500 gallons of water per minute from the mountain, which amounts to more than 2 billion gallons per year,” McSpadden said. “The mine would expand into the national forest with a new tailings facility, transmission lines, roads, and industrial lighting. This project and the Forest Services’ decision would threaten the clean water, air, and wild landscapes that sustain both wildlife and local communities.”

    Anna Darian, executive director of the Patagonia Area Resource Alliance told AZPM, “PARA is reviewing the US Forest Service’s Final Environmental Impact Statement for the Hermosa Project with our technical team and will respond accordingly. We remain committed to holding public agencies accountable for protecting the health of our community and the integrity of this unique ecosystem.”

    On Wednesday, The Santa Cruz County Board of Supervisors, Town of Patagonia and City of Nogales approved a community funding agreement with South32 to help fund mutually-agreed-upon investments across five broad categories throughout the county.

    Risner said that some of these early-actions investments amount to about $4 million in projects, and will help inform a future Community Protection and Benefits Agreement that will be completed later this year.

    The South32 Hermosa Project looks to mine two key federally designated minerals: zinc and manganese, as well as silver, lead and copper, to bolster national demand on renewable energy and electric vehicle supply chain.

    https://news.azpm.org/s/102876-forest-service-releases-final-environmental-impact-statement-for-hermosa-mine-project-near-patagonia/

    Share. Facebook Twitter Pinterest LinkedIn Tumblr Email

    Related Posts

    Malawi government suspends coal miner’s license over river pollution

    Senate Republicans send Trump resolution to lift mining ban near Boundary Waters Canoe Area

    US Senate repeals Biden-era ban on mining near Minnesota wilderness area Measure passes 50-49 to overturn a 20-year ban on mining near renowned Boundary Waters canoe area wilderness

    Don't Miss

    US companies eye Congo mining assets, including Rubaya, State Dept official says

    Global Policy 3 Mins Read

    U.S. companies are showing “significant” interest in Democratic Republic of Congo mining assets, including the…

    Seabed mining talks show key issues remain unresolved

    Vancouver-based mining company confirms the deaths of 9 of 10 workers kidnapped in Mexico

    Chile sets quarterly record in environmental permitting with mining projects totaling US$17.3bn

    Top Stories

    A red flower found nowhere else loses ground as mining expands in Brazil’s Amazon

    New Venezuelan Mining Law Obscures Old Corruption Problems

    Rethinking Environmental Clearance for Critical Mineral Mining

    Chile, US to Sign Agreements on Mining and Security

    Our Picks

    Zambians pay price amid Copperbelt mining boom

    Zambia mine regulator lifts suspension of operations at Mopani’s Mufulira mine

    Zambia dismisses US health warning after toxic spill in copper mining area

    Don't Miss

    Barrick Announces Evaluation of an Initial Public Offering of its North American Gold Assets

    State says health risks from Cottonwood mine waste are ‘minimal’

    Brazil dismantles hundreds of illegal dredges in major Amazon mining crackdown

    Weekly Newsletter

    Subscribe to our weekly Newsletter to keep up to date on the latest news in the metals, minerals and mining industry

    Copyright © 2025 - Metals Weekly. All Rights Reserved.

    Type above and press Enter to search. Press Esc to cancel.